Project
The Miami-Dade Water and Sewer Department (WASD) continues improving the water distribution system throughout Miami-Dade County. These enhancements include the installation of an 8-inch water main, water services, and fire hydrants along Riviera Drive between Hardee Road and east of SW 42 Avenue.
What to Expect
- Typical work hours are 8 a.m. - 4 p.m. Monday through Friday.
- Weekend work may occur as needed. Residents will receive advance notification.
- During construction work hours, there will be temporary road closures. Only local traffic allowed.
- All efforts are being made to minimize impacts to area residents and motorists.
- Restoration activities will take place upon the project’s completion and will address areas impacted by the construction.
- Schedule may change due to inclement weather or unexpected conditions.
- Please note that crews may need access to the exterior of properties adjacent to the work zone, but they will never request access to the interior of your home. The project team members have proper ID and safety vests.
Contact
For information about the project, please contact WASD Public Affairs Administrator Jeanette Gorgas at 786-835-6231 or by email at jeanette.gorgas@miamidade.gov.
When
This week, Aug. 4, the contractor will begin site preparation for the installation of the 8-inch water main along Riviera Drive between Hardee Road and east of SW 42 Avenue.
Week of August 11 through August 29
The contractor will begin the installation of the 8-inch water main along Riviera Drive, east of SW 42 Avenue heading north towards Hardee Road.
This is a mobile operation, and construction will occur in segments to minimize traffic impacts on area residents.
Anticipated Completion
The project is scheduled to start in August 2025, and the anticipated project duration is six months.
Why
Once completed, the project benefits include enhanced water quality, water pressure, and increased fire protection, allowing us to continue providing high-quality services.